At 670 MWp, the Taygete Energy Project will be the largest solar project to be built in the state of Texas.
Solar energy from the Taygete facility will be sold under a multi-year fixed priced power purchase agreement, which will bring the total developed by 7X in ERCOT to over 800 MWp.
Taygete
Pecos County, TX on ~2000 acres
670 MWp
Approximately 900,000
7X Energy is the originating and sole developer and owns 100% of the equity in the project
Confidential
Multi-year
Breaking ground for Phase I Q4 2019 and Phase II Q1 2020; Operational (COD) for Phase I Q1 2021 and Phase II Q2 2021
Taygete will produce over ~1,494,000 MWh of renewable energy in its first year of operation. This equates1 to: